§ 78-86. Final plat review and approval.  


Latest version.
  • Prior to final plat review and approval, the developer shall submit to the town commission evidence that all improvements have been completed in accordance with the approved plans and specifications and that other necessary requirements have been met. The following documents, data and information shall be given the town commission by the developer for review:

    (1)

    The subdivision plat, prepared in accordance with the provisions of F.S. ch. 177, and to the dimensions and in the manner prescribed by the office of the clerk of the circuit court of the county. The plat shall contain all data and information required by F.S. ch. 177, and the wording of required certificates shall be subject to the approval of the town attorney. All signatures necessary for final approval by the town commission shall appear on the plat at the time it is presented.

    (2)

    Any and all fees required for final approval and filing.

    (3)

    Certification of the developer's engineer that all improvements have been completed in accordance with the approval plans and specifications.

    (4)

    Results of all required laboratory tests taken of the improvements.

    (5)

    A set of as-built construction drawings.

    (6)

    A letter from the town engineer stating that he has inspected the completed improvements and that he recommends acceptance of the improvements and plat.

    (7)

    A letter from each utility owner stating that the subdivision work has been completed in a manner satisfactory to the company, insofar as the interests of the company are concerned.

    (8)

    A letter from each local, state or federal agency, if applicable, that any aspect of the subdivision work performed under that agency's jurisdiction or permit is acceptable.

    (9)

    Evidence satisfactory to the town attorney that all legal requirements of platting have been met.

(Ord. No. 106, § C(13), 11-9-1977)